Westfield Avenue public realm improvement scheme

Newham Council, in partnership with London Legacy Development Corporation, is improving the road layout and street environment along Westfield Avenue and the southern section of Waterden Road. This is a main thoroughfare in Newham, connecting Stratford Station and Westfield Stratford City with Queen Elizabeth Olympic Park and London Borough of Hackney.

The Westfield Avenue public realm improvement scheme will create a more pleasant street environment and enable more walking and cycling along the corridor. The project will provide a general uplift by creating a high street environment with wider pavements, segregated cycle tracks, better crossings and connections to local destinations, and more greenery and planting. These changes aim to create safe and attractive streets for everyone to enjoy, improving air quality and encouraging people to be more active and healthy.

Key project features

  • Create a high street environment where people will enjoy spending time
  • New and improved street lighting
  • Improve the cycling experience by introducing two-way segregated cycle tracks
  • Slow down vehicle speeds by introducing a 20mph speed limit
  • Improve the pedestrian experience by widening footways
  • Bus stops moved to more desirable locations
  • Additional pedestrian crossings
  • More greenery, trees and planting

Contact

Overall project queries

For queries about the overall project, including project objectives and designs, contact the Newham project team:

westfieldavenue@newham.gov.uk

Construction-related queries

For queries about construction, including disruption, parking suspensions, diversions, noise and timescales, contact the construction contractor:

KJE@Kensonhighways.com

Phases

Phases overview
Public consultation
Construction Phase 1
Construction Phase 2
Construction Phase 3

Construction Phase 1

January 16, 2024 - December 31, 2024

Phase 1 construction was delivered over 2024.

Improvements consisted of:

  • Improvements along Westfield Avenue including segregated cycleway, wider pavements, additional trees and planting
  • Additional cycle stands, electric cycle charging point and cycle maintenance stand
  • Relocated crossing to better align with pedestrian desire line
  • Cycle hire docking stations relocated to Stratford Walk
  • Pedestrian cycle crossing improved by widening to 20m
  • Relocated bus stops, loading bays and blue badge (accessible) parking spaces to improve access


Visualisation of Phase 1

Visualisation of Phase 1


Newham project team and Kenson contractors finalising design drawings (Dec 2023)