Romford Road Public Realm Improvement scheme

Romford Road is a key east-west route in Newham, connecting Stratford in the west to Little Ilford and the North Circular (A406) in the east. It provides important connections for pedestrians, cyclists and buses as well as private and commercial vehicles.

The key aim of the Romford Road Public Realm Improvement scheme is to create a better and safer street environment for residents, businesses, visitors and people travelling to destinations within the borough.

Visualisation of Romford Road, looking West at the junction of Upton Lane and Woodgrange Road.

Last updated 29 September 2026

Ongoing construction works in the sections mentioned below may affect traffic flows. This is due to temporary traffic lights, temporary bus stops, and parking / loading suspensions and access restrictions to side roads.

Junction 2 - Upton Lane / Woodgrange Road

Works to complete Junction 2 (Upton Lane / Woodgrange Road) will begin on 19 October 2026 and are expected to last until spring/summer 2027.

This substantial works package will include new segregated cycle lanes for safer cycle travel, a completely new junction layout with relocated crossing facilities to provide safer and easier crossing points, a new traffic light system to aid traffic flow, new soft landscaping to increase the biodiversity in the area, newly resurfaced carriageways for a smoother driving experience and large areas of ornamental paving on the footway to improve the overall look and feel of the area.

During this time there may be temporary traffic lights and other measures in place that may affect traffic flows during construction. We would like to confirm that full access will remain to all business premises at all times.

If you encounter any issues please do not hesitate to speak to a member of the team on site or contact our contractor, Marlborough Highways by phone on 020 7739 2976 or by e-mail on enquiries@marlboroughhighways.co.uk.

Phase 1 – Start date end of October 2026 - Expected completion end of November 2026

Phase 1A TM Drawing

Phase 2 – Start date beginning of January 2026 - Expected completion mid-January 2027

Phase 2A TM Drawing

Phase 2B TM Drawing

Phase 3 – Start date mid-January 2026 - Expected completion end of January 2027

Phase 3 TM Drawing

Phase 4 – Start date mid-February 2026 - Expected completion beginning of March 2027

Phase 4 & Phase 9 TM Drawing

Phase 5 – Start date beginning of March 2026 - Expected completion mid-March 2027

Phase 6 – Start date mid-March 2026 - Expected completion beginning of April 2027

Phase 7 – Start date mid-April 2026 - Expected completion end of April 2027

Phase 7 TM Drawing

Phase 8 – Start date beginning of March 2026 - Expected completion mid-March 2027

Phase 5 & Phase 8 TM Drawing

Phase 9 – Start date end of January 2026 - Expected completion beginning of March 2027

Phase 3 & Phase 9 TM Drawing

Phase 4 & Phase 9 TM Drawing

Phase 10 – Start date start of November 2026 - Expected completion mid-December 2026

Phase 10 TM Drawing

Phase 11 – Start date beginning of December 2026 - Expected completion mid-December 2026

Phase 12A – Start date end of March 2026 - Expected completion beginning of April 2027

Phase 6 & Phase 12A TM Drawing

Phase 12B – Start date beginning of April 2026 - Expected completion mid-April 2027

Phase 6 & Phase 12B TM Drawing

Phase 13 – Start date end of November 2026 - Expected completion mid-December 2026

Phase 13 TM Drawing

Phase 14 – Start date end of April 2026 - Expected completion end of April 2027

Junction 3 - Green Street / Richmond Road

Construction completed in July 2026 and was opened by the project team and Dr. Will Norman, London's Walking and Cycling Commissioner as shown in the video below.

Junction 7 - Little Ilford Lane / Colchester Avenue

Works to complete Junction 7 (Little Ilford Lane/ Colchester Avenue) began in June 2026 and are expected to last until January 2027. During this time there may be temporary traffic lights and other measures in place that may affect traffic flows during construction.

Click the PDF below to view a copy of the large banners that appear on the construction site.

Phase 3 – Works completed

Phase 4 – Start date end of June 2026 - Expected completion end of August 2026

Phase 4 TM Drawing

Phase 5 – Start date mid-August 2026 - Expected completion mid-September 2026

Phase 5 TM Drawing

Phase 6 – Start date beginning of September 2026 - Expected completion mid-September 2026

Phase 6a TM Drawing

Phase 6b TM Drawing

Phase 7 – Start date mid-September 2026 - Expected completion beginning of November 2026

Phase 7 TM Drawing

Phase 8 – Start date mid-October 2026 - Expected completion mid-November 2026

Phase 8a TM Drawing

Phase 8b TM Drawing

Phase 9 – Start date end of October 2026 - Expected completion beginning of December 2026

Phase 9a TM Drawing

Phase 9b TM Drawing

Phase 10A – Start date mid-November 2026 - Expected completion mid-December 2026

Phase 10a TM Drawing

Phase 10B – Start date beginning of November 2026 - Expected completion beginning of January 2027

Phase 10b TM Drawing

Phase 11 – Start date end of September 2026 - Expected completion beginning of January 2027

Phase 12 – Start date beginning of September 2026 - Expected completion mid January 2027

Phase 11 / 12a TM Drawing

Phase 11 / 12b TM Drawing

Please note that dates are indicative and may be subject to change as works progress.

Section F construction works

Construction works from no. 497 to no.577 Romford Road (northern footway), part of the section referred to as ‘Section F’, commenced in early February and are expected to be completed by October 2026. At some points during construction there may be temporary bus stop closures or bus stop relocations; and temporary parking and loading restrictions.

Note: To protect planting equipment against ongoing vehicle damage, we are installing boulders in some areas. If you notice any further damage, please report it to us at stromfordroad@newham.gov.uk

Contact us

Romford Road team | e: STRomfordRoad@newham.gov.uk

Visualisation of Romford Road at the junction of Green Street and Upton Lane

Visualisation of Romford Road, looking East at the junction with Richmond Road and Green Street

Visualisation of Romford Road, looking east towards Atherton Leisure Centre

Visualisation of Romford Road, looking East towards Atherton Leisure Centre

Phases

Phases overview
Phase 1: Public engagement on the overall scheme
Public engagement on the overall scheme
Phase 2: Public engagement on design (completed in 2023)
Public engagement on design (completed in 2023)
Phase 3: Public engagement on design (February/March 2024)
Public engagement on design (February/March 2024)
Phase 4: Statutory Consultation for Section B - South and Section D - South
Statutory Consultation for Section B - South and Section D - South
Phase 5: Statutory Consultation for Section G
Statutory Consultation for Section G
Phase 6: Statutory Consultation for Section F
Statutory Consultation for Section F
Phase 7: Statutory Consultation for Section I
Statutory Consultation for Section I
Phase 8: Richmond Road early engagement
Richmond Road early engagement
Phase 9: Statutory consultation - Junction 3
Statutory consultation - Junction 3
Phase 10: Statutory consultation - Junction 2
Statutory consultation - Junction 2

Richmond Road early engagement

June 12, 2025 11:00 PM - July 1, 2025 11:00 PM

Share your views on design changes to Richmond Road.