Skip to main content
Unfortunately, you can't participate in this project anymore because it has been archived

COLOURS OF MANOR PARK

The Project aims to deliver ‘creative’ building facade enhancement of the LBN-owned housing block situated at 1 Station Road / 681-691 Romford Road, London, E12 5AD at the junction of Romford Road. Investing in the appearance of the buildings at this junction was voted for by residents during the development of the Newham High Streets Programme. The project aims to continue engaging with the stakeholders to develop and finalise the design concept. The creative façade enhancement alongside the new murals aims to bring a sense of identity to Manor Park and make the area feel more welcoming. The project has two parts: 

  • Part 1 involves works to enhance the look and feel of the façade of 1 Station Road, above Manor Park Library. This aims to create a more welcoming entrance to Manor Park by improving the facade of the corner building. 
  • Part 2 involves the installation of one or more murals in the area surrounding 1 Station Road to highlight Manor Park’s local history and celebrate its identity. 

Over the course of spring/summer 2023, we'll be working with you to determine the preferred improvement types. The works are expected to finish by June 2024 and will address recommendations in Newham High Streets Report ‘Manor Park Library’ and ‘Colours of Manor Park’. The concept design proposal for the project will be developed through a community co-design process and is likely to include: 

  • Artistic enhancements to the building façade (e.g. murals)
  • Cleaning and repairs of tiled sections of the facade 

• Maintenance and repainting of balconies

• Cleaning and painting of windows, sills, and frames 

Your opinion on the types of enhancements and mural designs is important. Do you have any further ideas or want to comment on the proposed enhancement types above, please see the timeline at the bottom of the page for details on how to share your thoughts at each project stage.

Read through the Phases below for some more information. This page will be updated as the project progresses.

If you have any queries about the project or wanted to get in touch more generally, please email NewhamHighStreets@newham.gov.uk

You're viewing real-time data. Participant counts are continuously updated for administrators. Please note that regular users see cached data, which may result in slight differences in the numbers.

Phases

Phases overview
Phase 1: Strategic Recommendation
Strategic Recommendation
Phase 3: Selection of Design Team
Selection of Design Team
Phase 4: Community Co-design workshops
Community Co-design workshops
Phase 5: Community Co-design workshops 2
Community Co-design workshops 2
Phase 7: Key stakeholder consultation
Key stakeholder consultation
Phase 8: Preferred proposals consultation. We want your views!
Preferred proposals consultation. We want your views!
Phase 9: Design revisions including technical design, internal reviews.
Design revisions including technical design, internal reviews.
Phase 10: Final designs information session and design finalisation.
Final designs information session and design finalisation.
Phase 11: Final revisions and preparation before installation
Final revisions and preparation before installation
Phase 12: Building works procurement
Building works procurement

Selection of Design Team

December 1, 2022 12:00 AM - March 1, 2023 12:00 AM

Royffe Flynn Architects an experienced urban design company have been appointed to lead the next phases of engagement and design development. The murals will be designed by Newham-based The London Mural Company who have designed and implemented many iconic murals across London.